Method and management system

What is a preliminary hazard analysis (PHA)?

The first hazard screening for a project or plant, carried out early, before detailed design exists. Its purpose is to see the major hazards, and which design decisions they affect, while change is still cheap. Once the plant is built, the same finding costs far more to act on.

Its purpose

A preliminary hazard analysis asks “what in this could kill someone?” before detailed engineering begins. Its output is not a detailed risk table but a hazard list that steers the design.

What is looked at

  • the hazardous properties and quantities of the substances to be used,
  • energy sources: pressure, temperature, electricity, height, motion,
  • siting: distance to surroundings, neighbours and housing,
  • events that have happened at similar plants,
  • points not yet decided in the design where later change would be expensive.

Why timing decides everything

The cheapest way to remove a hazard is to design it out — choose a less hazardous substance, hold a smaller inventory, site the hazardous unit away from occupied areas. All of these are cheap early on; once the plant exists the same outcome can only be bought with added layers of protection, and at a higher price.

Relation to later analyses

The PHA sets the agenda for the detailed work that follows: which nodes go to HAZOP, which scenarios get a layer of protection analysis, which barriers are tracked in a bowtie. It does not replace any of them.

A common mistake

Dismissing the PHA because “there is no detail yet”. Major hazards are visible without detail; by the time the detail arrives it is too late to change them.